A Legacy of Renown
Before being integrated into Soleil Resources, the Youga mine was operated by several international mining giants, notably Endeavour and Avesoro, testifying to its strategic value and exceptional potential.
The Youga mine, an iconic site of the Burkinabe mining industry, received in 2003 its first industrial mining exploitation permit, for an initial period of 20 years. Entering production in 2008, this mine is located 185 km south of Ouagadougou, the capital of Burkina Faso.
In January 2022, mining activities were suspended until Soleil Resources
acquired the site. From this acquisition, revival works began in July 2024,
followed by production trials in September 2024.
Thanks to these efforts, the plant regained its normal production capacity in January 2025,
marking an important milestone in the revitalization of the mine.
The Youga mine is distinguished by its technical and operational specificities, demonstrating its strategic role in the Burkinabe mining industry. Thanks to modern infrastructure and optimized processes, the site maximizes the valorization of gold resources in the region. Here is an overview of the key elements that characterize its exploitation:
The Youga mine is based on a CIL (Carbon-In-Leach) process, exploited through several open-pit gold deposits.
The ore is processed in a 1.2 Mtpa (million tonnes per year) facility.
The site also processed ore from the Ouaré and Netiana/Balogo deposits.
At full operation, the Youga plant has the capacity to produce between 90,000 and 110,000 ounces of gold per year, contributing significantly to regional economic development.
Here are the key members who lead the strategic activities of the Youga Mine:
At the beginning of November 2026, Burkina Mining Company SA and all of its subcontractors had a total of 1,729 employees, including 12 non-nationals. The company promotes the development of local skills while bringing in international expertise to meet the needs of its projects. Its employment policy aims to balance stability and mobility within the organization.
Burkina Mining Company SA is carrying out a dynamic workforce mobilization, reaching a mobilization rate of 96% at the beginning of November 2026, compared to the projections for the year.
Key points:
Although women remain underrepresented within the overall workforce, they nevertheless hold senior-level responsibilities and have a strong presence among technicians and supervisory staff. Local community employment concerns are also well addressed, with priority given to local labor.
Our Commitments:
The staff of subcontracting companies currently represents more than 921 employees, and this number is set to grow with upcoming projects. The group plans to increase subcontracted employment in the coming months to support its development.
Please note:
The new Youga mine line is designed to process 1.2 million tonnes per year. The production circuit of the new plant will include a grinding sector, a cone crusher, conveyors, a screen, a crushed ore stock, a 3MW Ball mill and hydrocyclones for product size classification. The cyclone overflow will be sent to a thickener, then the thickened slurry pumped to the CIL circuit. The CIL circuit will consist of six leaching basins, with an oxygen plant. The loaded carbon will be processed in the existing gold recovery circuit and gold doré bars will be produced in the existing gold room. CIL tailings will be pumped to the existing tailings facility.